What is unworkable weather?

Unworkable weather — in Dutch onwerkbaar weer — is weather in which work on site cannot reasonably continue: frost, snow, prolonged rain or storm. In Dutch construction and civil engineering this is not a matter of judgement but of measurable criteria, set out in a dedicated collective agreement.

There are two sides to it. Practically, you cannot lay bricks or pour concrete in frost, and working at height in a storm is dangerous. Financially, someone has to carry the standstill; there is a scheme for that, under which the employer first pays for a number of days and can afterwards claim a benefit through the national scheme.

How the Dutch scheme works

Waiting days

Waiting days under the Dutch unworkable weather scheme2 daysFrost, black ice and snowfall, perwinter season (1 November to 31 March)2 daysStorm, per calendar year19 daysHeavy rainfall, per calendar year
Waiting days for Dutch construction and civil engineering under the collective agreement. The employer pays these days before a benefit through UWV can be claimed. Frost counts per winter season (1 November to 31 March), storm and heavy rainfall per calendar year. Exact thresholds and the number of waiting days can change between agreement periods, so always check the current text.

The criteria are objective. For frost, temperatures at fixed measuring moments overnight and in the morning are used; for rain, the number of minutes of precipitation within working hours. Always check the current text of the agreement, since the exact thresholds and the number of waiting days can change from one agreement period to the next.

What it means on site

Related terms