What is the striking point of an arch?

The striking point is the centre from which the curve of a masonry arch is set out. Put the point of a compass — or the fixed end of a string — at the striking point and swing an arc, and you describe exactly the curvature the arch must take. In Dutch the term is porringpunt, from porring: the curvature of an arch or vault, meaning the height of the crown above the line joining the two springings.

Why the position of that point decides everything

The form of an arch follows directly from where you place the striking point relative to the springing line (the line joining the two springings):

Where the striking point sits decides the arch formOne point on the middle of thespringing line→Semicircular arch; the radiusequals half the spanOne point below the springing line→Segmental arch; the lower thepoint, the flatter the archOne point above the springing line→Stilted or raised archTwo points, left and right ofcentre→Pointed arch: on the springingpoints equilateral, closer togethera drop arch, further apart a lancetSeveral points (three, five ormore)→Basket-handle or elliptical arch,each segment with its own centre
Position of the striking point relative to the springing line (the line joining the two springings) and the arch form that results.

Flat arch forms work the same way: the radiating lines from a striking point determine how the joints fan out and therefore how the load is passed along.

Setting it out in practice

  1. Draw the springing line and the centreline of the opening on the substrate or on a sheet of board.
  2. Decide the rise you want and mark the crown.
  3. Construct the striking point: it lies on the vertical centreline, where the distances to the crown and to both springings are equal.
  4. Drive a nail or screw at the striking point, attach a string or batten and swing the arc.
  5. Build the centring (the temporary former) from that drawing, and lay the arch on it.
Setting out an arch in practice1Draw springing line and centrelineOn the substrate or on a sheet of board.2Mark the crownDecide the rise you want first.3Construct the striking pointOn the vertical centreline, equally far from the crown and both springings.4Swing the arcUse a nail or screw at the striking point with a string or batten.5Build the centring and lay the archThe temporary former is made from that drawing.
Work full size, 1:1 on a sheet of plywood, and leave the centring in place until the mortar has gained sufficient strength.

Points to watch

Related terms