Pile head cropping is cutting the concrete heads of driven piles down to the correct level in order to expose the reinforcement. The exposed bars then project into the ground beam or pile cap that is cast afterwards, forming the structural connection between pile and foundation.

Why it is necessary

A precast concrete pile can never be driven to exactly the required level. One pile meets resistance sooner than the next, and piles are deliberately supplied overlength. After driving, the heads therefore stand at different heights above working level. All heads have to be brought to a single level and the concrete cover removed so the steel is bare. Without that anchorage the ground beam merely rests on the pile instead of being structurally tied to it.

How it is done

Points to watch