A utility search is the enquiry into which cables and pipes lie in the ground at a location, made before any digging starts. The point is to avoid damage to electricity, gas, water, telecoms and drainage networks — damage that is both dangerous and expensive.

In the Netherlands this is centrally organised. The enquiry is called a KLIC notification (Kabels en Leidingen Informatie Centrum, the cables and pipes information centre) and runs through the Kadaster, the Dutch land registry. The legal basis is WIBON, the Dutch act on the exchange of information about above and below ground networks.

The Dutch KLIC notification

Anyone digging with mechanical equipment — an excavator, an auger or other machinery — must submit an excavation notification. The deadlines:

There is also an orientation request for the design stage; it does not entitle you to dig.

Elsewhere

Other countries organise this differently but the duty of care is the same. In the UK, utility plans are requested from the network operators or through a central service before excavation; in the United States the “call before you dig” number arranges free marking-out of buried services. Whatever the system, digging without an enquiry leaves you liable for the damage.

Practical tips