A strip foundation is a continuous strip of concrete beneath the load-bearing walls of a building. It is the most common form of shallow foundation: an uninterrupted concrete beam that distributes the weight of the walls evenly across the ground.

How does a strip foundation work?

The strip foundation follows the exact line of the load-bearing walls. Wherever there is a wall, there is a concrete strip beneath it. The weight of the wall is distributed over a larger ground area via the strip, preventing the structure from settling.

The strip is always wider than the wall above — typically 20-30 cm wider on each side. This increases the bearing area.

When do you use a strip foundation?

Suitable for Not suitable for
Garages with masonry walls Soft peat soil
Sheds with single- or half-brick walls Ground with variable bearing capacity
Garden buildings on firm subsoil Very heavy structures (multiple storeys)
Garden walls and boundary walls Areas with high water table

Construction

A standard strip foundation for a garage or shed:

Layer Description
Subsoil Load-bearing, undisturbed ground
Sand bed 5-10 cm of poured and compacted sand as a levelling layer
Concrete Reinforced concrete strip, minimum 20 cm high
Plinth masonry Damp-proof masonry from foundation to ground level
Wall The actual wall of the building

Dimensions (guidelines)

Application Width Height Depth (below ground level)
Garden wall 30 cm 15 cm 60 cm
Shed (half-brick) 35 cm 20 cm 60-80 cm
Garage (single-brick wall) 45 cm 20-25 cm 60-80 cm
Dwelling 50-60 cm 25-30 cm 80 cm (structural engineer calculation)

Building a strip foundation yourself

1. Set out — Stretch lines between profile boards to mark the exact position

2. Excavate — Dig the trench to the correct depth and width. Keep the sides as clean as possible

3. Compact the base — Firmly compact the bottom of the trench

4. Apply sand bed — 5-10 cm of sand, levelled

5. Place reinforcement — Minimum 2 bars diameter 10 mm at the bottom, on spacers (cover 3 cm)

6. Formwork — Only needed if the soil is crumbly. In firm clay, the trench itself can serve as formwork

7. Pour concrete — C20/25 concrete, poured in one go (not layer by layer)

8. Curing — Minimum 7 days, cover in hot weather to prevent drying too

Concrete specs for a DIY strip foundation2 × Ø 10 mmMinimum reinforcement bars at thebottom of the strip3 cmConcrete cover over the reinforcement,placed on spacers7 daysMinimum curing time for the pouredconcrete
Key reinforcement and curing figures from the step-by-step build.

quickly

Strip foundation vs. pier foundation

Strip foundation Pier foundation
Shape Continuous strip Separate concrete blocks
Suitable for Masonry walls Timber post structures
Material use More concrete Less concrete
Load distribution Even under entire wall Point load per pier
DIY More work, but feasible Simpler