What is a cone penetration test report?

A cone penetration test (CPT) report presents the results of pushing an instrumented cone into the ground: for each test location, a plot shows how much resistance the soil offers at every depth. A geotechnical engineer uses it to interpret the soil profile, and above all where a firm bearing layer begins. Electrical CPTs are carried out to EN ISO 22476-1. In the Netherlands, where soft soils make CPTs routine, the report is called a sonderingsrapport.

What does the plot show?

Application

A practical way to read a CPT plot:

  1. Use the friction ratio to identify the soil. Indicative values: sand about 0.6-1.0%, clay about 2-6%, peat about 5-10%. Above the water table, values can deviate considerably.
  2. Combine it with cone resistance. Low qc with a high friction ratio points to soft clay or peat; high qc with a low ratio points to sand or gravel.
  3. Look for the bearing layer. For piles, what counts is a thick layer with consistently high cone resistance, not a single spike.
  4. Compare several tests. Layer depths vary across a site; one CPT does not describe the whole footprint.
  5. Leave the design to the engineer. Pile toe level and capacity are determined by the structural or geotechnical engineer under Eurocode 7.
Reading cone resistance and friction ratio togetherLow qc with a high friction ratio→Points to soft clay or peatHigh qc with a low friction ratio→Points to sand or gravelThick layer with consistently highcone resistance→What counts as bearing layer forpilesThin sand band with high peaks,soft soil beneath→Not the bearing layer: a pile canstill settle
How combinations in a CPT plot point to soil type and bearing layer. Compare several tests; pile toe level and capacity are determined by the structural or geotechnical engineer under Eurocode 7.
Indicative friction ratio (Rf) by soil typeabout 0.6-1.0%Sandabout 2-6%Clayabout 5-10%Peat
Indicative friction ratio values for reading a CPT plot. Above the water table, values can deviate considerably. Combine with cone resistance (qc); the design is left to the engineer.

Common mistake: taking a thin sand band with high peaks for the bearing layer. If soft soil lies beneath it, a pile can still settle.